plan-sealing-tips-tricks

Plan Sealing – Tips and Tricks

By Ryan Ashworth

The Federal Government’s Homebuilder stimulus package has really ramped up projects with many due for completion late this year or early next year.  This means a heap more plan sealing requests over the coming months, placing enormous pressure on Authorities and plan sealing timeframes.

In a previous article, we looked at how earlier plan sealing could be achieved (click here). While getting an early start is crucial, there are some tips and tricks that have recently helped our clients with their approvals and we share these below.

1.  Involve Authorities, Contractors and All Consultants

Some Authorities have been responding very positively to their role in aiding economic recovery. As such, we have been able to reach the right people to negotiate the following outcomes:

  • Same day turnaround from Council engineers for plan sealing inspections including same day sign off,
  • Pragmatic outcomes to plan sealing works such as deferring minor non-conformances to the on-maintenance stage,
  • File note/email acceptance between officers to minimise time delays associated with Requests for Information (RFI’s).

Similarly, working with civil contractors has resulted in them responding positively to their role in the plan sealing process including:

  • Co-ordinating and rescheduling the construction program to prioritise plan sealing triggers and complete these early (at no extra cost),
  • Securing supply chains to better manage lead times for material and labour to deliver on plan sealing priorities,
  • Ongoing weekly inspections to review plan sealing progress and apply corrective actions.

The key has been early involvement and a deeper understanding of key deliverables beyond just the construction of a project to save time where it makes a difference.

2.  Uncompleted Works Bonding

Thresholds for bonding differ for each local authority. Some allow earlier bonding trigger points, others apply different bonding factors, and some have very specific definitions in their criteria to name just a few. It is extremely important to be familiar with these requirements so that we can find a good balance between managing bond amounts while avoiding unnecessary bonding delays. In most instances bulk earthworks and retaining works must be 100% compete but there are some other nuances as follows:

  • Brisbane City Council generally do not permit bonding of trunk works so it is crucial to have these works completed for on-maintenance early,
  • Moreton Bay Regional Council allow bonding of civil works at 50% completion,
  • Logan City Council generally do not allow bonding of the last stage of development,
  • Redland City Council manage their own water infrastructure and require sewer and water to be completed prior to plan sealing,
  • Sunshine Coast Council define bonding at the stage of ‘non-essential infrastructure’ which has recently been interpreted as the point after footpath construction (near the end of the project),
  • Bonding factors will vary for each Authority and typically range between 120% to 150%. It is important to apply the correct bonding factors,
  • Your project may include separate components to be completed at different times e.g. stormwater basins, landscaping, rehabilitation, etc. Opportunities to prepare separate bonds for each component may assist with earlier bond releases,
  • Some authorities have very specific terminology and definitions required for bonds. If in doubt, ask the question early to avoid the pain of needing to raise new bonds.

Importantly, other Authorities such as the Water Authorities need to be satisfied for plan sealing. Urban Utilities and Unitywater allow bonding at the 50% stage however as mentioned above, Redland Water requires completion of water and sewer whereas Logan Water does not allow bonding of a final stage of development.

While the above items form the typical rules for bonding, we have had some Authorities allow relaxations on a case by case basis to assist with expediting plan sealing.

3.  Know the Council and Approval Condition Requirements

There are ways where conditions for plan sealing can be managed well before the application process. One way is to thoroughly review conditions of approval at the Development Approval stage and recognise any conditions that impact timing of plan sealing. In some instances timing/trigger points can be negotiated to on-maintenance rather than at plan sealing. Likewise, if there is any ambiguity in the interpretation of plan sealing conditions we have worked with Authorities to seek early clarification in writing. Quite often the officer assessing the plan sealing application is not the same officer who set the conditions or issued the approvals. By having clear interpretation confirmed in writing, this overcomes the ambiguity and the unnecessary delays that ensue from RFI’s.

While the above is by no means a full coverage of the plan sealing process, we see that they are well worth considering given the potential to save weeks in the plan sealing process.

If you would like to learn more about the specific examples and how they may apply to your project, please do not hesitate to reach out to our team.

How Smart Stormwater Solutions Can Pay Off in a Big Way

By Kelly McKendry -Director of Water & Environment We often have clients approach us seeking guidance around stormwater management and quite often the key focus is on the size of stormwater basins on their development sites. The solution may seem quite obvious, and that is the reduce the size of the basin. Unfortunately, we see … Continue reading How Smart Stormwater Solutions Can Pay Off in a Big Way

What is the Outlook for Civil Construction Rates?

By Andrew Ngo, Principal Engineer, PEAKURBAN Several clients have recently approached us seeking a current outlook on civil constructions rates across Southeast Queensland. And although we are in a good position to share our observations of the market, we also thought it was worthwhile reaching out to several reputable civil contractors for their input. We … Continue reading What is the Outlook for Civil Construction Rates?

Tips for Developing Steep and Sloping Land

By Troy Schultz (Principal Engineer) & Kerry Saron (Senior Urban Designer) It’s hard to believe that there was once a time in SEQ when developers could readily buy flat and serviceable land. Now we see that development sites tend to be steeper and harder to service. Despite these sites being more challenging, with some careful … Continue reading Tips for Developing Steep and Sloping Land

Plan Sealing – Tips and Tricks

By Ryan Ashworth The Federal Government’s Homebuilder stimulus package has really ramped up projects with many due for completion late this year or early next year.  This means a heap more plan sealing requests over the coming months, placing enormous pressure on Authorities and plan sealing timeframes. In a previous article, we looked at how … Continue reading Plan Sealing – Tips and Tricks

Different Sites Require Different Stormwater Solutions

By Kelly McKendry, Director – Water & Environment, PEAKURBAN It is par for the course that when preparing a Development Application in Queensland a Stormwater Management Plan (SMP or SWMP) is generally required. However, a SWMP shouldn’t give you the same solution for every site. For instance, stormwater detention may not be required for all … Continue reading Different Sites Require Different Stormwater Solutions

Where are the next Masterplanned Community projects going to be?

By Troy Schultz, Principal Engineer, PEAKURBAN In recent years I’ve noticed an increasing trend of developer’s seeking acquisition sites with minimal planning risk (inside urban footprint, appropriately zoned and preferably with an approval in place). Who could blame them given the political and regulatory minefield they are facing these days. More and more clients tell … Continue reading Where are the next Masterplanned Community projects going to be?

Managing Costs and Value in the “New World”

By Andrew Ngo, Principal Engineer, PEAKURBAN There is little doubt that cost control is a hot topic now. While it has always been important to manage costs regardless of the market cycle, the question though is whether the necessary spending was more than it should have been in the first place. We previously wrote an … Continue reading Managing Costs and Value in the “New World”

Key Points when Negotiating Infrastructure Agreements

By Brent Thomas A well-constructed Infrastructure Agreement (IA) provides certainty for the developer and Authority regarding the delivery of various trunk infrastructure items. A good IA will clearly set out the obligations of each party, the funding and extent of infrastructure to be provided, identify any offsets and mechanisms for refunds, specify trigger points and … Continue reading Key Points when Negotiating Infrastructure Agreements

PEAKURBAN welcomes Brendon Bolt to the Water & Environment Team.

Brendon has over 18 years’ experience practicing in the field of environment and water resources. His vast experience in local and regional scale projects includes water balance modelling, hydrologic modelling, 1D/2D hydraulic modelling, flood mapping in GIS, conceptual / detailed design, environmental management and permitting, erosion and sediment control, water quality modelling, drainage assessment and … Continue reading PEAKURBAN welcomes Brendon Bolt to the Water & Environment Team.

PEAKURBAN expands into Water and Environment!

We are delighted to announce that Kelly McKendry has joined PEAKURBAN as Director of our newly created Water and Environment Team! Kelly has over 18 years’ experience in stormwater quality and quantity management as well as flood modelling. Notably, Kelly recently managed her own consultancy and is highly regarded in the industry having completed many … Continue reading PEAKURBAN expands into Water and Environment!

Getting Those Credits You’re Entitled to: Converting Non-Trunk Infrastructure to Trunk Infrastructure

By Andrew Ngo We previously wrote about the conversion application process and how to obtain the infrastructure credits that you are entitled to on your projects. Our previous article can be found in the link below. https://www.peakurban.com.au/conversion-applications-get-the-credits-you-are-entitled-to/ To recap, a conversion application is an application that developers can make under the Planning Act 2016 (Section … Continue reading Getting Those Credits You’re Entitled to: Converting Non-Trunk Infrastructure to Trunk Infrastructure

Unlocking Land and Delivering Affordability

By Brent Thomas (Published in UDIA Qld Establish Magazine #112 – Spring 2019) In all growth corridors across South East Queensland (SEQ), it is widely known that there are major land holdings in the urban footprint (UF) that have been identified as suitable for urban development, but have been locked up due to any range … Continue reading Unlocking Land and Delivering Affordability

What’s the cost per lot across SEQ Growth Corridors

By Troy Schultz We know that developers need to act quickly to secure development sites. Quite often a quick, informed assessment of a site using typical revenue and cost data is sufficient to enable a site value to be ascertained and a high level offer put in front of the vendor. To assist our clients, … Continue reading What’s the cost per lot across SEQ Growth Corridors

Updated EDQ Road Standards – What’s the impact on your project?

EDQ have released a new version of their ‘Street and Movement Network’ guideline. The new guideline can be accessed here. There are some significant changes included in the latest revision which may adversely affect development yield and cost. Some more notable changes include: Road reserve widths and pavement widths have changed for all road types, … Continue reading Updated EDQ Road Standards – What’s the impact on your project?

Launching PEAK Ai – Improving Project Design, Planning and Execution

The engineering and construction industry is at the cusp of a new era, with new applications and tools that change how companies design, plan and execute projects. At PEAKURBAN we are always trying to maximise the value and improve the level of service we offer to our clients. Quite often this involves developing smarter infrastructure … Continue reading Launching PEAK Ai – Improving Project Design, Planning and Execution

Changes to the Security of Payment Act

By Troy Schultz, Principal Engineer, PEAKURBAN At PEAKURAN, we aim to stay on top of key changes so that we are equipped to continue protecting our client’s interests. You may be aware that the Building Industry Fairness Act 2017 (Qld) (BIFA) commenced on 17 December 2018. This replaces the Building and Construction Industry Payment Act … Continue reading Changes to the Security of Payment Act

Managing Costs and Value in a Slower Market

By Andrew Ngo, Principal Engineer, PEAKURBAN There’s a lot of media articles about slower sales and a tighter credit market across the country, especially in Sydney and Melbourne. Having been through a couple of ‘challenging’ times previously, this inevitably affects market confidence with developers attentions more sharply focused on finding cost reductions and optimising value … Continue reading Managing Costs and Value in a Slower Market

PEAKURBAN Turns 2

It’s hard to believe that it’s been 2 years since we opened the doors at PEAKURBAN. You never really know how things will turn out but the journey thus far has been both exciting and fulfilling. We started PEAKURBAN believing that the old way of doing business (at least in engineering circles) was fast disappearing … Continue reading PEAKURBAN Turns 2

PEAKURBAN Planning and Survey

We are delighted to welcome Tim Connolly (Director – Planning) and Nathan Wilson (Principal Planner) to the PEAKURBAN Planning and Survey team. Tim has over 30 years’ experience in statutory and strategic planning and has worked on many large and complex projects including Warner Lakes, Riverbank, Riverparks, Park Vista, Capestone, Brentwood, The Meadows and Ridgeview. … Continue reading PEAKURBAN Planning and Survey

How to Get Your Survey Plans Sealed Earlier

A key milestone for any urban development project is plan sealing, that critical event that facilitates registration of titles and settlements, and the trigger for project revenue to be realised. In talking with several developers, they describe an increasingly arduous and frustrating process of back and forward, multiple inspections, delays and inefficiencies. Whilst there’s always … Continue reading How to Get Your Survey Plans Sealed Earlier

Can’t get stormwater discharge consent? You may not need it.

Whether or not a Legal Point of Discharge (LPOD) exists has been for a long time, a very grey and murky area. The consequences of this ambiguity have meant stalled projects, refusal of development applications, cost over-runs and quarantined development sites. We have heard of some developers even needing to store or pump out stormwater! … Continue reading Can’t get stormwater discharge consent? You may not need it.

Conversion Applications – Get the credits you are entitled to.

In talking with several developers recently, it seems that the issues around trunk and non-trunk infrastructure and what’s creditable v. non creditable is alive and well. A few developers that we’ve spoken with are quite frustrated in having received development approvals imposing conditions that require them to deliver (without credits) what they believe to be … Continue reading Conversion Applications – Get the credits you are entitled to.

Infrastructure Agreements: Negotiating the Right Deal.

Negotiating the right deal in an Infrastructure Agreement (IA) is critical in ensuring the commercial viability of a project. On too many occasions we have seen IA’s that are one sided, impose excessive infrastructure standards and as a consequence result in works or financial contributions that stall projects for long periods of time. The last … Continue reading Infrastructure Agreements: Negotiating the Right Deal.

Is Poor Contract Administration Costing You Money?

By Ryan Ashworth, Civil Engineer at PEAKURBAN Poor contract administration can lead to lower development profits, protracted disputes, missed settlements and sub-standard infrastructure. Whether it’s a lack of site experience, a poorly constructed contract or just a lack of understanding of what’s required, it seems to be a common problem we hear throughout the development … Continue reading Is Poor Contract Administration Costing You Money?

Engineering value in a tough market – the site acquisition challenge

By Andrew Ngo, Principal Engineer at PEAKURBAN 2017 so far has been an intensely competitive year when it comes to buying development sites. Despite this, over the last couple of months we’ve helped four clients successfully acquire new projects – three residential development sites (1,830 lots) and one retirement project (145 sites). So, what have … Continue reading Engineering value in a tough market – the site acquisition challenge

Giving up too much land?

A number of clients have come to us recently raising concerns about losing too much developable land, due to easements and wider infrastructure corridors being imposed by Authorities.  The reason, they advise, is for future maintenance requirements.  What many clients may not be aware of is the maintenance method of “pipe bursting” which in many cases, means the … Continue reading Giving up too much land?